Project Update August
2009
The Northwestern Water and Sewer District is
constructing water distribution and sanitary sewer collection infrastructure
to serve the State of Ohio’s Jobs Ready Site (JRS) bordered by US 20,
SR 420 and Pemberville Road. The total project cost is estimated
at 7.2 million dollars, with one third of the cost being underwritten
by a grant from the State of Ohio and one third being funded by the
East Ohio Gas Company.
The water portion of the project consists of
14,300 feet of water main, a high pressure booster pumping station
and one 500,000-gallon water tower. In addition, a 1.5 million-gallon
clear well will also be built. The water line will not only
enhance fire protection capability in the area but will also provide
public water service to those residents along the route who wish
to tap.
The water tower, located on SR 582, began construction
in June. It
is scheduled for completion in July of 2010. The water line portion
of the project is scheduled for bid in mid-September with construction
scheduled to begin in early November. Completion is scheduled
for February of 2010. Construction of the booster pumping station
and clear well is planned to begin in April of 2010.
The sewer line and pumping facilities will
be incorporated into the Stony Ridge and Lemoyne sanitary project
tentatively scheduled for bid in late September of 2009. The JRS portion of the project
consists of 5,200 linear feet of gravity sewer, 10,000 linear feet
of sanitary force main, and 2 pump stations. This project
will require roughly one year for construction with tentative completion
in November of 2010. Sewer taps could then begin in late November
of 2010.
Related documents :
JRS Project Timeline (PDF posted August 31, 2009)
JRS Sewer Line Map (PDF posted August 31, 2009)
JRS Water Line Map (PDF posted August 31, 2009)
JRS Water Tap Amortization Schedule (PDF posted August 31, 2009)
Letter to Residents RE construction information (PDF posted August 31, 2009)
Letter to Residents RE well testing (PDF posted September 22, 2009)
Letter to Residents RE construction update (PDF posted November 19, 2009)
Water Tower Construction Photos:
Site Cleaning Before/After 6/27/2009 (PDF)
Rebar Installation 6/30/2009 (PDF)
Foundation Pour 6/30/2009 (PDF)
GPS Locating 7/1/2009 (PDF)
Crane Construction 7/6/2009 (PDF)
First Lift Pour 7/8/2009 (PDF)
Lift Pour #2 7/28/2009 (PDF)
Lift Pour #5 8/6/2009 (PDF)
Lift Pour 8/21/2009 (PDF)
Lift Pour (cont.) 8/21/2009 (PDF)
Access Hatch & Top of Tower Views 9/1/2009 (PDF)
Ring Rebar Installation 9/2/2009 (PDF)
Lifting Cables/Tank Cone Assembly 9/17/2009 (PDF)
Tank Bowl Fabrication 9/15/2009 (PDF)
Tank Bowl Assembly 10/2/2009 (PDF)
Bowl Sandblasting & Preliminary Painting 10-20-2009 (PDF)
Ring Beam Pour 10-23-2009 (PDF)
Logo Painting & Inspection 10-24-2009 (PDF)
Bowl Raising 11-8-2009 (PDF)
|