District Project Update

Monday, October 26, 2018

Bowling Green, Ohio

The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 19,000 customers in Wood, Sandusky, and Hancock counties. Although many of our projects are performed underground, our utility work can impact roads throughout our service area. The District will announce updates when additional projects are under contract. Updates and additions are highlighted in bold and underlined.

Perrysburg Township – Starbright Subdivision Waterline Replacement

Through October, short-term, intermittent lane restrictions are possible throughout the Starbright subdivision for restoration work.

Perrysburg Township – Sanitary Sewer Improvements

Through November, short-term intermittent lane restrictions are possible throughout Perrysburg Township for sewer work and manhole repair. Project complete: November.

Rossford & Perrysburg Township – Waterline Replacement

Through November, intermittent lane restrictions are possible on Vineyard and Groce Streets in Rossford and on Riverbend Court and White Road in Perrysburg Township for waterline replacement. Restoration work will take place in the spring. Project complete: November.

Weston – Waterline Replacement

Through December, lane restrictions are possible on Center Street from Main Street to Euler Road and on Euler Road, between Center Street and Silver Street for waterline replacement. Waterline work on Cygnet Road in Cygnet will be announced. Project complete: December.

Other Projects

Hydrant Flushing

Through November, weekdays from 8 am until 3:30 pm, crews will be flushing and testing fire hydrants in Perrysburg Township and Rossford. Residents are advised to flush water from their taps if the water becomes discolored. For more information: Visit  Hydrant & Main Line Flushing Info Page
For a full list of projects on and off-road, please visit our Northwestern Water & Sewer website