District Project Update

**COVID-19 PROJECT IMPACT: WATER AND SEWER CONSTRUCTION PROJECTS ARE CONSIDERED ESSENTIAL WORK AND MAY CONTINUE AS SCHEDULED AT THE DISCRETION OF THE CONTRACTOR. **

Rossford – Lime City Road Waterline Replacement *PROJECT UPDATE*
Through May, intermittent lane restrictions are possible on Lime City Road between Dixie Highway and Marilyn Drive for waterline replacement.   Through May, lane restrictions are possible on Schreier Road near Lime City Road for waterline replacement.  Project complete: May.  Project investment: $770,000.

Rossford – Eagle Point Sewer Replacement
Through April, lane and shoulder restrictions are possible on Eagle Point west of Colony Road for restoration work.  Project complete: April 2020. Project investment: $1.2 million.

Rossford – Deimling Road Water & Sewer Line Installation *PROJECT UPDATE*
Effective immediately through May, Deimling Road, from Simmons to Crossroads Boulevard, is closed to through traffic for water and sewer line installation.  Project complete: June. Project investment: $502,000.

Troy Township – NSG Sewer Line Installation
Through April, lane restrictions are possible on Garling Road just west of Pemberville Road. Project complete: November. Project investment: $760,000.