District Project Update

Bowling Green, Ohio

The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 19,000 customers in Wood, Sandusky, and Hancock counties. Although many of our projects are performed underground, our utility work can impact roads throughout our service area. The District will announce updates when additional projects are under contract. Updates and additions are highlighted in bold and underlined.

Henry County, Damascus Township – Hydrant Replacement

Hydrant work on State Route 65 and 110 and hydrant flushing in the Village of McClure is now complete, hydrant maintenance will continue through September.

Northwood – East Broadway Water Valve Installation

Through October, shoulder restrictions are possible on Wales and Andrus Roads for water valve installation. Project complete: October. Project investment: $480,000.

Northwood/Perrysburg & Lake Townships – Water Main Installation

Through August, lane restrictions are possible at Tracy and McNerney Roads for restoration. Additionally, at this time, lane restrictions are possible at the intersection of Oregon Road and Caple Boulevard. Project complete: August. Project investment: $155,000.

Perrysburg Township – Sanitary Sewer Improvements

Through August, short-term intermittent lane restrictions are possible throughout Perrysburg Township for restoration. Project complete: August. Project investment: $998,000.

Rossford – Sewer Lining Project

Through August, watch for shoulder restrictions and construction crews on roads north of Eagle Point Road for sewer lining. Project complete: August. Project investment: $767,000.

District-Wide Hydrant Flushing

Through September, weekdays from 8 am until 3:30 pm, crews will be flushing hydrants in Lake Township, parts of Northwood, and the Village of Millbury. Residents are advised to flush water from their taps if the water becomes discolored. For more information: Visit Hydrant & Main Line Flushing Info Page