District Project Update

Reminder: The District office will be closed, Monday, November 11th in observance of Veterans Day.

McComb – Stormwater Separation Project

Through November, lane and alley restrictions are possible north and south of Main Street between High and Center Streets in McComb for stormwater separation. Project complete: December. Project investment: $152,000.

Millbury – Sewer Lining

Through December, short-term intermittent lane restrictions are possible throughout the Village of Millbury for sewer lining. Project complete: January. Project investment: $840,000.

Northwood – East Broadway Water Valve Installation

Through November, shoulder restrictions are possible on Wales and Andrus Roads for water valve installation. Project complete: December. Project investment: $480,000.

Northwood – Tracy Road Waterline Repair

Tracy Road, between Andrus and Wales Roads, is now open. Future closure for waterline repair will be announced.

Rossford – Vernis Street Sewer Replacement Project

Through November, lane restrictions are possible on Vernis Street for sewer replacement. Project complete: November. Project investment: $115,000.

Rossford – Eagle Point Sewer Replacement

Through April 2020, construction crews and lane and shoulder restrictions are possible on Eagle Point west of Colony Road for sewer replacement. Project complete: April 2020. Project investment: $1.2million.

Rossford – Deimling Road Water & Sewer Line Installation

Through December, lane and shoulder restrictions are possible on Deimling Road, from Simmons to Lime City Roads, for water and sewer line installation near the Amazon construction site. Project complete: January 2020. Project investment: $502,000.

Troy Township – Pemberville Road Waterline Installation

Through November, lane restrictions are possible on Pemberville Road, from US 23 to SR 582 for waterline installation at the NSG facility. Project complete: November. Project investment: $760,000.

Weston – Meter/Meter Pit Relocation

Through November, short-term water service shut-offs and pressure fluctuations are possible in various locations throughout the Village of Weston for meter pit relocation: Project complete: November. Project investment: $303,000

District-Wide Hydrant Flushing

Through November, on weekdays from 8 am until 3:30 pm, crews will be flushing hydrants in Rossford and Perrysburg Township. Residents are advised to flush water from their taps if the water becomes discolored. For more information: Visit Hydrant & Main Line Flushing Info Page