Perrysburg Township: Ampoint Industrial Park Waterline Replacement
Work throughout Aimpoint Industrial Park and on Third Street, between Glenwood Road and D Street for waterline replacement is now complete.  Project investment: $994,000.

Perrysburg Township: Sewer Lining
Through December, lane restrictions are possible in Perrysburg Township north of SR 795, west of 75, and south of the turnpike, for sewer rehabilitation.  Project complete:  February 2021.  Project investment: $1,230,000.

Rossford: Waterline Replacement
Through September, lane restrictions are possible on Santus Drive, Valley Drive, and on Glenwood Road in Rossford.  Project complete: October.  Project Investment: $1.5 million.

Rossford – Tree Streets Waterline Replacement *UPDATE*
Through September, lane restrictions are possible on Maple Street, Oak Street, Walnut Street, and Superior Street for paving, sidewalk, and restoration work.  Project complete: September. Project investment $740,000.

District-Wide Hydrant Flushing
Through October, weekdays from 7:30 am until 4 pm, crews will be flushing hydrants in various locations throughout Lake Township, Northwood, Walbridge and Rossford.  Residents are advised to flush water from their taps if the water becomes discolored.  For more information:  https://nwwsd.maps.arcgis.com/apps/View/index.html?appid=17eef70e88ca43a4ac3b8649fb263199