District Project Update

BOWLING GREEN, Ohio, – The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 20,000 customers in Wood, Henry, Sandusky, and Hancock counties.  Although many of our projects are performed underground, our utility work can impact roads throughout our service area.  Updates and additions are highlighted in bold and underlined.

REMINDER: The District office remains closed to the public until further notice due to COVID-19.  Our customer call center will be closed Monday, October 12th in observance of Columbus Day.  Please contact your local sheriffs’ dispatch in case of an emergency

McComb: Scott Street Sewer Interceptor Project *NEW PROJECT*
Effective today, lane restrictions are possible on Scott Street from the new wastewater treatment plant to Cooper Street for sewer replacement.  Project complete: January.  Project investment: $400,000.

Perrysburg Township: Sewer Lining
Through December, lane restrictions are possible in Perrysburg Township north of SR 795, west of 75, and south of the turnpike, for sewer rehabilitation.  Project complete:  February 2021.  Project investment: $1,230,000.

Rossford: Waterline Replacement
Through October, lane restrictions are possible on Santus Drive, Valley Drive, and on Glenwood Road in Rossford.  Project complete: November.  Project Investment: $1.5 million.

Rossford – Tree Streets Waterline Replacement *PROJECT COMPLETE*
Waterline work and restoration work on Maple Street, Oak Street, Walnut Street, and Superior Street is now complete.  Project complete: September. Project investment $740,000.

District-Wide Hydrant Flushing
Through October, weekdays from 7:30 am until 4 pm, crews will be flushing hydrants in various locations throughout Rossford.  Residents are advised to flush water from their taps if the water becomes discolored.  For more information:  https://nwwsd.maps.arcgis.com/apps/View/index.html?appid=17eef70e88ca43a4ac3b8649fb263199