BOWLING GREEN, Ohio, – The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 20,000 customers in Wood, Henry, Sandusky, and Hancock counties.  Although many of our projects are performed underground, our utility work can impact water and sewer service in addition to roads throughout our service area.  Updates are highlighted in bold and underlined.

Henry County Waterline: Waterline Installation
Through November, lane and shoulder restrictions are possible starting in Weston on Euler Road (CR N) from Van Tassel Road to SR 65 for waterline installation.  Project investment $4.9 million. Project complete: Spring 2023.

Lake Township: Water Tower
Through August, crews will be constructing a 1.5-million-gallon elevated water tank near Lemoyne Road between Latcha and Hanley Roads.  Residents can expect additional construction vehicle traffic and possible shoulder restrictions in this area.  Project investment: $4 million.  Project complete:  October 2022.

Perrysburg: Willowbend Pump Station & Force Main Replacement
Through November, River Road (SR 65) between Brittany Road and Seminary Road will be closed for pump station installation.  Detour: Roachton Road; Fort Meigs Road.  Local access will be maintained.  Project Cost: $2.5 Million.  Project complete: December 2022.

Perrysburg Township: Ford Road Pump Station Replacement 
Through September, Ford Road, between White Road and Lindsay Drive will be closed for sanitary sewer installation.  Detour: Simmons Road; SR-795; White Road.  Through April 2023, expect additional construction traffic on Ford Road between White Road and Lindsey Road for pump station replacement and relocation.   Project investment: $7.7 million.  Project complete: April 2023.

Walbridge: Waterline Replacement
Through September, lane restrictions and closures are possible on and along Main Street between Guy and Clinton Streets for water line replacement.  Residents and businesses will be notified of any service interruptions.  Project Cost: $600,000.  Project complete: November.

District-Wide Hydrant Flushing
This week
, weekdays from 8 a.m. until 3:30 p.m., District crews will be flushing hydrants north of Roachton Road in Perrysburg Township.  Starting August 29th and running through November, crews will move to the Toledo water service area including Rossford, Walbridge, Lake Township, and parts of Northwood.  Residents are advised to flush water from their taps if the water becomes discolored.  Avoid doing laundry until water is clear.  Click here for more information.

District-Wide Valve Maintenance
Through August, crews will be in areas between US 20 and SR 795, and areas north of the Ohio Turnpike in Perrysburg Township for valve maintenance.  This work involves turning valves on waterlines, which can occasionally cause water to become discolored.  Residents are advised to flush their taps if this occurs.  Valve maintenance work will continue in various locations throughout The District through December.

###

Our goal is to be the premier water and wastewater provider in Northwestern Ohio. We are committed to sound financial management, responsible environmental stewardship, responsive public service, superior customer service, and responsible economic growth.  We strive to field a skilled, respectful, and cooperative workforce dedicated to the highest professional and ethical standards; we support them with appropriate training and technology.

Theresa Pollick, Office: 419.354.9090 X 193, Cell: 419.806.1018; Email: tpollick@nwwsd.org