BOWLING GREEN, Ohio – The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 20,000 customers in Wood, Henry, Sandusky, and Hancock counties. Although many of our projects are performed underground, our utility work can impact water and sewer service and roads throughout our area. Updates are highlighted in bold and underlined.
Northwood: Sewer Lining Project
Through August, intermittent lane restrictions are possible in various locations throughout Northwood for sewer lining. Project investment: $830,000. Project complete: August.
Northwood: Farnstead Waterline Replacement *UPDATE*
Waterline installation on Farnstead Drive, between Tracy Road and Sheffield Place, is complete. Additional road closures and lane restrictions on Farnstead are possible for paving in August. Meter pit installation will take place by fall of this year. Project investment: $978,000. Project complete: September.
Perrysburg Township: Starbright Sewer Rehabilitation
Through September, intermittent lane restrictions are possible throughout the Starbright subdivision for sewer rehabilitation. Project investment: $863,000. Project complete: September.
Perrysburg Township: Ford Road Pump Station Replacement
Through July, intermittent closures of Ford Road, between White Road and Lindsay Drive, are possible for finish work. Detour: Simmons Road; SR-795; White Road. Project investment: $7.7 million. Project complete: July.
Rossford: Windsor Drive Water and Sewer Main Replacement
Through July, Windsor Drive, between Eagle Point Road and Hoffman Avenue, is closed for storm sewer installation and paving. No through traffic. Local access is permitted. Project investment: $1M. Project complete: August.
Rossford: Various Streets Waterline Project
Through August, intermittent road closures are possible on Rosedale Place and Island View Drive for waterline installation. Local access will be maintained. Additional work on Maybar Drive, Schreier Road, Elm Tree Road, Rossway Avenue, and Bergin Street will be announced. Project investment: $2 million. Project complete: December.
District Hydrant Flushing *UPDATE*
Through August, District crews will be flushing hydrants in the following areas: Perrysburg, Lake, and Troy townships. Additional locations will be announced. You can track the progress of our hydrant flushing program by clicking here to see the updated Hydrant Flushing Progress Map.
District-Wide Landscaping *UPDATE*
Through August, crews will perform landscaping work in various locations throughout our service area. Work may involve lane and shoulder restrictions.
###