BOWLING GREEN, Ohio – The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 20,000 customer accounts in Wood, Henry, Sandusky, and Hancock counties. Although many of our projects are underground, our utility work can impact water and sewer service and roads throughout our area. Updates are highlighted in bold and underlined. All work is weather permitting.
Reminder: The District office is closed Monday, October 13th, in observance of Columbus Day. Call 419-354-9090 for water and sewer emergencies in your county.
Middleton and Center Township: SR 582/Dunbridge Water and Sewer Project *UPDATE*
Sewer, water, and restoration work in Dunbridge and along Dunbridge Road from SR 582 to Poe Road is complete. Road closures and lane restrictions along Dunbridge Road near SR 582 for sewer pump station installation will be announced. Project investment: $13.1 million. Project complete: December 2025.
Northwood: Curtice Road Pump Station Replacement *UPDATE*
Through December, the intersection of Bihl Avenue and Olde Curtice Road may be closed for pump station replacement work. Local access will be maintained. Project investment: $370,000. Project complete: December.
Northwood, Rossford, Lake Township: Waterline Replacement Project
Through October, lane restrictions are possible on Glenwood Road from SR 795 to Buck Road for waterline installation. Traffic is maintained by flaggers. Through October, Oregon Road, between Wales Road and Andrus Road, is closed for waterline replacement. Local traffic is maintained. Suggested alternate route, Wales Road to Tracy Road to Andrus Road. Additional work in Northwood, Lake Township, and Rossford will be announced. Project investment: $5.6 million. Project complete: January.
Rossford: Jennings Road Waterline and Sanitary Sewer Replacement *UPDATE*
Waterline and sanitary sewer installation work is complete on Jennings Road from Eagle Point Road to Veterans Memorial Park. The City of Rossford will continue storm sewer and pavement work until further notice. District project investment: $1.8M.
District Hydrant Flushing
Through October, District crews will be flushing hydrants in various locations including Northwood, Rossford, Walbridge, Millbury, Lake Township and Troy Township. You can track the progress of our hydrant flushing program by clicking here to see the updated Hydrant Flushing Progress Map.