BOWLING GREEN, Ohio – The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 20,000 customer accounts in Wood, Henry, Sandusky, and Hancock counties. Although many of our projects are underground, our utility work can impact water and sewer service and roads throughout our area. Updates are highlighted in bold and underlined. All work is weather permitting.
Northwood: Woodville Road Waterline Replacement
Through September, lane restrictions are possible on Woodville Road between Lemoyne Road and Owen Road for waterline work. Project investment: $1.8 million. Project complete: October.
Northwood, Rossford, and Lake Township: Waterline Replacement Project.
*PROJECT COMPLETE*
Waterline and restoration work in the following locations is now complete:
- Moline in Lake Township
- Wales Road from Tracy Road to E. Broadway Street
- Glenwood Road from SR 795 to Buck Road.
Project investment: $5.6 million.
Various Locations: Landscaping and Restoration *COMPLETE*
Seasonal landscape restoration work carried over from winter is now complete. Ongoing landscaping activities will continue throughout The District service area.
District-Wide Hydrant Flushing *UPDATE*
Through July, weekdays from 8 a.m. until 3:30 p.m., District crews will be flushing hydrants Middleton and Perrysburg Townships. Residents are advised to flush water from their taps if the water becomes discolored. Avoid doing laundry until water is clear. CLICK HERE to see the updated hydrant flushing progress map.