District Project Update

BOWLING GREEN, Ohio – The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 20,000 customer accounts in Wood, Henry, Sandusky, and Hancock counties. Although many of our projects are underground, our utility work can impact water and sewer service and roads throughout our area. Updates are highlighted in bold and underlined. All work is weather permitting.

Northwood: Woodville Road Waterline Replacement *UPDATE*
Effective Thursday, October 8 through October, Woodville Road between Lemoyne Road and Owen Road will be reduced to one lane in both directions for paving. Through November, lane restrictions are possible on Woodville Road between Lemoyne Road and Owen Road for waterline work. Project investment: $1.8 million. Project complete: November.

Rossford: Jennings Road Sewer Lining
Through November, mobile sewer inspection and sewer lining vehicles may be staged in various locations on Jennings Road from Eagle Point Drive to Veterans Memorial Park for sewer lining. While full lane closures are not anticipated, motorists should expect periodic, temporary lane restrictions while work is actively underway. Project investment: $475,000. Project complete: November.

Walbridge and Lake Towsnhip: E. Union Street Water Main Replacement *NEW PROJECT*
Effective, the week of Monday, October 5 through November, lane restrictions are possible on E. Union Street between Dixon Street and Martendale Place in Walbridge for water main replacement. Residents will be notified of water service interruptions by door tag or phone. Project investment: $284,000. Project complete: November.

District-Wide Hydrant Flushing
Through October, on weekdays from 8 a.m. to 3:30 p.m., District crews will flush hydrants in Northwood and Lake Township. Residents are advised to flush their taps if the water becomes discolored and to avoid doing laundry until the water runs clear. CLICK HERE to see the updated hydrant flushing progress map.