The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 19,000 customers in Wood, Sandusky, and Hancock counties. Although many of our projects are performed underground, our utility work can impact roads throughout our service area. The District will announce updates when additional projects are under contract. Updates and additions are highlighted in bold and underlined.

The District office will be closed Monday, September 2 in observance of Labor Day. For water and sewer emergencies, contact (419) 354-9001.

McComb – Stormwater Separation Project

Through November, lane and alley restrictions are possible north and south of Main Street between High and Center Streets in McComb for stormwater separation. Project complete: December. Project investment: $152,000.

Millbury – Sewer Lining

Through October, short-term intermittent lane restrictions are possible throughout the Village of Millbury for sewer lining. Project complete: November. Project investment: $840,000.

Northwood – East Broadway Water Valve Installation

Through October, shoulder restrictions are possible on Wales and Andrus Roads for water valve installation. Project complete: October. Project investment: $480,000.

Perrysburg Township – Sanitary Sewer Improvements

The sewer improvement project in Perrysburg Township is now complete. Project investment: $998,000.

Rossford – Sewer Lining Project

Through September, watch for shoulder restrictions and construction crews on roads north of Eagle Point Road for sewer lining. Project complete: September. Project investment: $767,000.

Rossford – Deimling Road Water & Sewer Line Installation

Through November, lane and shoulder restrictions on Deimling Road are possible through October for water and sewer line installation near the Amazon construction site. Project complete: November. Project investment: $318,000.

Troy Township – Waterline Installation

Through November, lane restrictions are possible on Pemberville Road, from US 23 to SR 582 for waterline installation at the NSG facility. Project complete: November. Project investment: $760,000.

Weston – Meter/Meter Pit Relocation

Through October, short-term water service shut-offs and pressure fluctuations are possible in various locations throughout the Village of Weston for meter pit relocation: Project complete: November. Project investment: $303,000

District-Wide Hydrant Flushing

Through September, on weekdays from 8 am until 3:30 pm, crews will be flushing hydrants in Lake Township and parts of Northwood. Effective in September, crews will begin hydrant flushing in Rossford and Perrysburg Township. Residents are advised to flush water from their taps if the water becomes discolored. For more information: Visit Hydrant & Main Line Flushing Info Page