District Project Update

Reminder: The District office will be closed, Monday, November 11th in observance of Veterans Day.

McComb – Stormwater Separation Project

Stormwater separation work north and south of Main Street between High and Center Streets in McComb is now complete. Project investment: $152,000.

Millbury – Sewer Lining

Sewer lining work in the Village of Millbury is now complete. Project investment: $840,000.

Northwood: East Broadway Waterline Repair

Effective Monday, November 11, through Friday, November 22, East Broadway Street, from Wales Road to Andrus Road will be closed for water line repair. Detour: Wales Road; Tracy Road; Andrus Road. Additionally, on Friday, November 22 through December, lane restrictions are possible on East Broadway Street, from Wales Road to Andrus Road for waterline repair. Local access will be maintained. Project complete: January 2020. Project investment: $500,000.

Northwood – Tracy Road Waterline Repair

Upcoming closure for Tracy Road, between Andrus and Wales Roads for waterline repair will be announced.

Rossford – Vernis Street Sewer Replacement Project

Through November, lane restrictions are possible on Vernis Street for restoration. Project complete: November. Project investment: $115,000.

Rossford – Eagle Point Sewer Replacement

Through April 2020, construction crews and lane and shoulder restrictions are possible on Eagle Point west of Colony Road for sewer replacement. Project complete: April 2020. Project investment: $1.2million.

Rossford – Deimling Road Water & Sewer Line Installation

Through December, lane and shoulder restrictions are possible on Deimling Road, from Simmons to Lime City Roads, for water and sewer line installation near the Amazon construction site. Project complete: January 2020. Project investment: $502,000.

Troy Township – Pemberville Road Waterline Installation

Through November, lane restrictions are possible on Pemberville Road, from US 23 to SR 582 for waterline installation at the NSG facility. Project complete: November. Project investment: $760,000.

Weston – Meter/Meter Pit Relocation

Through November, short-term water service shut-offs and pressure fluctuations are possible in various locations throughout the Village of Weston for meter pit relocation: Project complete: November. Project investment: $303,000

District-Wide Hydrant Flushing

Through November, on weekdays from 8 am until 3:30 pm, crews will be flushing hydrants in Rossford and Perrysburg Township. Residents are advised to flush water from their taps if the water becomes discolored. For more information: Visit Hydrant & Main Line Flushing Info Page