Northwood: Tracy Road Waterline Replacement Project Update

BOWLING GREEN, Ohio, – The Northwestern Water and Sewer District (The District) announces the following updates to the Tracy Road Waterline Replacement project in Northwood.  Updates are highlighted in bold and underlined.

Northwood: Tracy Road Waterline Replacement *UPDATE*
Effective, Thursday, April 20 the intersection of Florence Avenue and Tracy Road will be closed.  Use alternate route.  Additional closures of Florence Avenue at Tracy Road will be announced.  Through Friday, April 21, Tracy Road between Florence Avenue and West Andrus Road is closed.  Use an alternate route.  Additional lane restrictions on Tracy Road from Florence Avenue to Wales Road for waterline replacement will be announced.  Road closures on Florence Avenue and Andrus Road at Tracy Road, and service interruptions will be announced.  Project investment: $1.9 million. Project complete: January 2024.