BOWLING GREEN, Ohio—The Northwestern Water and Sewer District announces the following update to the SR 582/Dunbridge water and sewer project in Middleton and Center townships. Updates are highlighted in bold and underlined. Work was extended due to weather. All work is weather permitting.
Middleton and Center Township: SR 582/Dunbridge Water and Sewer Project *UPDATE*
Effective Monday, January 13 and Tuesday, January 14, Mercer Road, just south of SR 582, will close daily (7 am until 5 pm) for sewer work—alternate Route: SR 582 to SR 25 to Devils Hole Road—additional closures of Mercer Road to be announced. Through December 2025, intermittent lane and shoulder restrictions are possible in Dunbridge and along Dunbridge Road from SR 582 to Poe Road for sewer work. Additionally, intermittent lane and shoulder restrictions are possible on SR 582 between SR 25 and Dunbridge Road for water and sewer line installation. Project investment: $13.1 million. Project complete: December 2025.