District Project Update

Bowling Green, Ohio

The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 20,000 customers in Wood, Henry, Sandusky, and Hancock counties.  Although many of our projects are performed underground, our utility work can impact roads throughout our service area.  Updates and additions are highlighted in bold and underlined.  Work may be delayed due to weather.

Lake Township: Water Tower

Through August 2022, crews will be constructing a 1.5-million-gallon elevated water tank near Lemoyne Road between Latcha and Hanley Roads.  Residents can expect additional construction vehicle traffic and possible shoulder restrictions in this area.  Project complete:  September 2022.  Project investment: $4 million.

McComb: Waterline Replacement Project

Through May, lane restrictions are possible on South Main Street, between Park Drive and Liberty Street, on Todd Street, near the railroad tracks, and on West Cooper Street between Liberty Street and Rader Road, for paving and restoration.  Project complete: June.  Project Investment: $600,000.

McComb: Sanitary/Storm Sewer Replacement Project

Through May, SR 235 will be closed from the railroad tracks (just south of SR 613) to Bond-Preble Street for sanitary sewer replacement. Detour: SR 613, I-75, US 224.  Watch for lane and ally restrictions between S. Main Street and Bond Preble.  Additional intermittent closures of SR 613 for final paving and restoration will be announced. Project complete: July. Project investment: $950,000.

Perrysburg Township: Waterline Replacement

Through May, lane restrictions are possible on North and South Bramblewood, Bridgewood, and Cliffwood Streets in Perrysburg Township for paving and restoration.  Project complete: May.  Project Investment: $1.5 million.

Perrysburg Township: Sewer Lining

Through July, lane restrictions are possible in Perrysburg Township, on Mandell Road, Lime City Road, and Glenwood Road, between I-75 to SR 795, and in Perrysburg Heights for sewer rehabilitation.  MAP OF EXACT LOCATIONS. Project complete:  August.  Project investment: $1,230,000.

Weston: Sewer Rehabilitation Project

Effective May 10 through August, lane restrictions and service interruptions are possible on Ohio Street, and on Ash and Center Streets near Ohio Street.  Sewer work will also include work in other areas in Weston but is expected to have a minimal impact on roads and sewer service.  Project complete:  August.  Project investment: $900,000.

District-Wide: Restoration

Beginning Tuesday, May 4 through Friday, May 14, Glenwood Road, between Beech Street and Santus Drive may be reduced to one lane for paving work.  Traffic may be maintained by flaggers or automated signal.  Additionally, at this time, lane restrictions are possible on Curtice Road, east of I-280 in Northwood, and along Main Street in Weston for paving.  Work may be delayed due to weather. Lane restrictions and short-term road closures are possible in various locations in McComb, Perrysburg Township, for restoration work. Additionally, miscellaneous areas throughout The District will also be restored.

District-Wide: Valve Maintenance

District valve maintenance work is paused until further notice.  Future valve maintenance work will be announced.

District-Wide: Bulk Water Station Upgrade Project

Through May 14, The Lemoyne Road bulk water station is currently operating on a temporary dispensing unit to install permanent PIN unit.